The site is hitting critical milestones as it shifts from construction to operational readiness. Electrical infrastructure has reached a major juncture, with the 33kV overhead line commissioned to the transformer yard. Following successful factory acceptance testing, two 1,250 kVA plant transformers are back on site, setting the stage for full site energisation in early November.
Structural progress across the processing circuits is nearing completion. Workers have finished installing the regrind mill, while structural steel work for the WHIMS and MGS areas stands at 90% capacity. Shaking tables are also 80% complete, providing the backbone for the upcoming separation process. As the physical plant takes shape, the company has begun training initial operating personnel and is finalizing logistics contracts to ensure the concentrate reaches its destination once production begins.