The company has appointed GenCap Mining Advisory to structure project financing, aiming to secure capital well before the official development commitment. This move coincides with ongoing technical preparations, including the procurement of long-lead equipment and advanced site infrastructure design. Ausenco Engineering, alongside SLR Consulting, continues to oversee the technical planning required to maintain the project timeline.
Permitting efforts remain a core priority, with the company currently working with the Bureau of Land Management to finalize the Environmental Impact Statement. On-site, Integra is validating its 2025 feasibility study assumptions through a crushing pilot plant that has already processed 39,000 tons of material. Additionally, the company is upgrading existing infrastructure, including a truck shop and access bridge, to ensure the site meets operational standards for future construction.