S&P 500 5,235.18 +1.02%EUR/USD 1.0840 +0.21%GBP/USD 1.2710 +0.14%USD/JPY 149.50 −0.18%BRENT $82.40 −0.81%BTC $67,800 −0.21%GOLD $2,341 +0.55%NASDAQ 16,420.55 +0.74%S&P 500 5,235.18 +1.02%EUR/USD 1.0840 +0.21%GBP/USD 1.2710 +0.14%USD/JPY 149.50 −0.18%BRENT $82.40 −0.81%BTC $67,800 −0.21%GOLD $2,341 +0.55%NASDAQ 16,420.55 +0.74%
A daily business newspaper · Founded in 2026

Money Talk

Finance and markets: business, quotes, gold, energy and releases.

Snowy 2.0 Costs Could Reach $25 Billion as Delays Mount

Australia’s Snowy 2.0 pumped-hydro expansion, originally framed as a roughly $2 billion project, is now projected to cost between $22.2 billion and $25 billion. The latest estimate, reported in October, comes as more than a third of the tunnelling remains unfinished and the expected completion date has slipped to 2029.

Snowy 2.0 Costs Could Reach $25 Billion as Delays Mount

The expansion of the Snowy Mountains Hydro-electric Scheme is intended to add 2.2 GW of pumped-hydro capacity and 350,000 megawatt-hours of storage. It would link two reservoirs with tunnels about 27 kilometres long, pumping water uphill when electricity demand is low and releasing it through turbines when demand peaks, including during periods of weak wind and solar generation.

Australia has about 8.5 GW of conventional and pumped hydropower operating across more than 120 stations, supplying 5 to 7 per cent of national electricity. The Australian Energy Market Operator’s draft 2026 Integrated System Plan estimates the country will need 27 GW of storage by 2030 and 55 GW by 2050. The government’s Powering Australia Plan targets 82 per cent renewable electricity by 2030 and net-zero emissions by 2050.

Snowy 2.0’s cost estimates rose before construction was well advanced. A 2017 feasibility study put the cost at $5.4 billion to $6.9 billion. The government made a $6.1 billion investment decision in 2018, before geological studies were complete and before environmental works and transmission lines had been approved. The project received approval in 2020, and three tunnel-boring machines were commissioned.

One machine became stuck in unexpected soft ground 150 metres into a 15-kilometre excavation and remained there for almost a year. After returning to work, it became stuck several more times. In 2023, the Labour government introduced an incentivised contract structure for new operators, Italian company Webuild. Strikes by tunnel workers over pay and working conditions added further delays. By August that year, the projected cost had reached $12 billion, with completion expected in 2028. A 2020 independent review had already warned of risks to cost and schedule, but its recommendations were not heeded.

The International Hydropower Association and its Australian members released a roadmap in February to accelerate pumped-storage development. IHA president Malcolm Turnbull said pumped storage was essential to a successful clean-energy transition and affordable electricity, and called for policy settings and market signals to get projects built. He said the technology and economics worked, but that decisive action was needed.

Snowy 2.0 is intended to support a reliable grid as Australia retires coal and gas generation and expands intermittent wind and solar. Its rising cost and prolonged construction have also highlighted the consequences of proceeding before key assessments are complete.