S&P 500 5,235.18 +1.02%EUR/USD 1.0840 +0.21%GBP/USD 1.2710 +0.14%USD/JPY 149.50 −0.18%BRENT $82.40 −0.81%BTC $67,800 −0.21%GOLD $2,341 +0.55%NASDAQ 16,420.55 +0.74%S&P 500 5,235.18 +1.02%EUR/USD 1.0840 +0.21%GBP/USD 1.2710 +0.14%USD/JPY 149.50 −0.18%BRENT $82.40 −0.81%BTC $67,800 −0.21%GOLD $2,341 +0.55%NASDAQ 16,420.55 +0.74%
A daily business newspaper · Founded in 2026

Money Talk

Finance and markets: business, quotes, gold, energy and releases.

Norway freezes new data center grid reservations until 2027

Norwegian data centers have sought about 34 gigawatts of grid capacity—more than the country’s roughly 25 GW peak demand. On 9 November, transmission operator Statnett halted new reservations, with the pause set to last until at least August 2027, as the government also announced a licensing scheme barring new crypto-mining sites.

Norway freezes new data center grid reservations until 2027

Only 0.8 GW of requested data center capacity is connected today. A further 4.2 GW has been reserved, 10.8 GW is in the queue and 18 GW remains at the inquiry stage. Statnett has also stopped approving facility functionality under the Regulation on System Responsibility (fos) § 14 while it develops requirements for how data centers respond to grid disturbances, change their load and limit fluctuations. Projects with existing reservations retain their place, but still need approval to connect; current connections are unaffected.

About half of the queued capacity is sought by the end of 2028. With new reservations frozen until August 2027 at the earliest—and grid construction still required—those timelines appear difficult for both established operators and new entrants. Statnett’s pause comes as data center demand threatens Norway’s longstanding power surplus.

Crypto restrictions and pressure on supply

Norway has six operating crypto data centers with combined capacity of about 0.2 GW. The new licensing scheme bars new sites, while existing operators cannot obtain additional grid capacity and could face restrictions after transitional arrangements expire. Some are converting to AI. In the NO3 price area, data center power use fell from late 2025 after a large site stopped mining ahead of conversion, then began rising again.

Hydropower supplies about 90% of Norway’s electricity, and decades of surplus have kept prices below those in most of Europe. Under normal hydrology, higher demand from data centers and other consumers could reduce net exports by 71%, from 14.3 terawatt-hours in 2027 to 4.1 TWh in 2030. In a dry year, Norway could become a net importer, with winter prices reaching about €290 per megawatt-hour.

The government wants data centers to help develop gas power with carbon capture and storage (CCS) and offshore wind, but both take time to build. Statnett’s pause gives the operator more control over incoming demand while new supply is pending, and helps limit price risks for households and industry. Across Europe, grid operators are also tightening connection rules: Great Britain, Germany and Denmark have done so since 2025, favoring projects that can demonstrate progress.

Share article
TelegramXFacebook

When reusing this material a link to Money Talk is required.

Comments (0)

Leave a comment

No comments yet. Be the first!